During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources?

During project planning in a matrix organization, the project manager determines that additional human resources are needed. From whom would he request these resources?


A. Project manager
B. Functional manager
C. Team
D. Project sponsor


Answer B