A project manager must publish a project schedule. Activities, start/end times, and resources are identified. What should the project manager do NEXT?

A project manager must publish a project schedule. Activities, start/end times, and resources are identified. What should the project manager do NEXT?



A. Distribute the project schedule according to the communications management plan
B. Confirm the availability of the resources
C. Refine the project management plan to reflect more aceurate costing information
D. Publish a bar chart illustrating the timeline


Answer B


Learn More :