You have been assigned as project manager for a large telecommunications project. This one year project is about halfway done. The project team consists of five sellers and 20 of your company's employees. You want to understand who is responsible for doing what on the project. Where would you find such information?
A. Responsibility assignment matrix
B. Resource histogram
C. Bar chart
D. Project organization chart
Answer: A Responsibility assignment matrix