During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a _____ for the second half of the project.

During the first half of the project, five team members left for other projects without being replaced, two team members went on vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is BEST if you create a _____ for the second half of the project.


A. Work breakdown structure
B. Resource histogram
C. Staffing management plan
D. Responsibility assignment matrix


Answer C