Which of the following is not considered to be a characteristic of a project?
A. An established objective
B. A clear beginning and end
C. Complex tasks
D. Only for internal use
E. Never been done before
Answer: Only for internal use
A. An established objective
B. A clear beginning and end
C. Complex tasks
D. Only for internal use
E. Never been done before
Answer: Only for internal use