A project manager had a complex problem to solve and made a decision about what needed to be done. A few months late, the problem resurfaced. What did the project manager most likely not do?
A. Proper risk analysis
B. Confirm that the decision solved the problem
C. Have the project sponsor validate the decision
D. Use an Ishikawa diagram
Answer: D Use an Ishikawa diagram