You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally ad you do no have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?

You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally ad you do no have the ability to directly reward their performance. The project is difficult, involving tight date constraints and challenging quality standards. Which of the following types of project management power will likely be the MOST effective in this circumstance?


A. Referent

B. Expert

C. Penalty

D. Formal


Answer: B Expert