A project manager must publish a project schedule. Activities, start/end times, and resources are identified. What should the project manager do NEXT?

A project manager must publish a project schedule. Activities, start/end times, and resources are identified. What should the project manager do NEXT?




A. Distribute the project schedule according to the communications management plan.

B. Confirm availability of resources

C. Refine the project management plan to reflect more accurate costing information.

D. Publish a bar chart illustrating the timeline


Answer: B Confirm the availability of resources