Which of the following is not one of the recommended guidelines for developing useful work package estimates?
A. Estimates should be made by those responsible for the work
B. Use several people to estimate the same work
C. Estimates should be based on normal conditions
D. Estimates should include a normal level of contingency
E. Estimates should be independent of other projects
Answer: D. Estimates should include a normal level of contingency