Which of the following is not one of the bottom-up approaches to estimating project time and cost?
A. Parametric procedures applied to specific tasks
B. Estimates for the WBS work packages
C. Learning curve
D. Template method
E. All of these are bottom-up approaches
Answer: Learning curve