Typical kinds of costs found in a project include
A. Direct costs
B. Project overhead costs
C. General and administrative costs
D. Only A and B are included
E. A, B, and C are all included
Answer: A, B, and C are all included
A. Direct costs
B. Project overhead costs
C. General and administrative costs
D. Only A and B are included
E. A, B, and C are all included
Answer: A, B, and C are all included