You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?

You know when you have arrived at the optimal solution in using the Time-Cost CPM Scheduling model analysis when what happens?




A. You have found the critical path
B. You have run out of crash time
C. You no longer have a linear relationship with costs
D. You have reached the minimum total cost
E. You have run out of crash costs






Answer: D