You have just joined the project management office after five years of working on projects. One of the things you want to introduce to your company is the need to create and utilize WBSs. Some of the project managers are angry that you are asking them to do "extra work". Which of the following would be the BEST thing you could tell the project managers to convince them to use WBSs?

You have just joined the project management office after five years of working on projects. One of the things you want to introduce to your company is the need to create and utilize WBSs. Some of the project managers are angry that you are asking them to do "extra work".
Which of the following would be the BEST thing you could tell the project managers to convince them to use WBSs?


A. Tell them it will prevent work from slipping through the cracks
B. Tell them that it is not needed
C. Tell them it is required only if the project involves contracts
D. Tell them it is the only way to identify risks



Answer A