Which of the following is CORRECT in regard to the Control Scope process?

Which of the following is CORRECT in regard to the Control Scope process? 




A. Effective scope definition can lead to a more complete project scope statement
B. The Control Scope process must be done before scope planning
C. The Scope Control process must be integrated with other control processes
D. Controlling the schedule is the most effective way of controlling scope


Answer C