A scope change has been suggested by one of the stakeholders on the project. After careful consideration and a lot of arguing, the change control board has decided to reject the change. What should the project manager do?

A scope change has been suggested by one of the stakeholders on the project. After careful consideration and a lot of arguing, the change control board has decided to reject the change. What should the project manager do? 


A. Support the stakeholder by asking the board for the reason for the rejection
B. Suggest to the stakeholder that the next change they request will be approved
C. Record the change request and its result
D. Advise the change control board to make sure they create approval processes before the next change is proposed


Answer C