Which of the following documents is used as the baseline for evaluating whether requests for changes or additional work are contained within or outside the project's boundaries and guiding the team through the Executing processes?

Which of the following documents is used as the baseline for evaluating whether requests for changes or additional work are contained within or outside the project's boundaries and guiding the team through the Executing processes?



A. Project Charter

B. Project Scope Statement

C. Project Requirements Documentation

D. WBS Dictionary


Answer: B