Which of the following sequences is in the proper order:

Which of the following sequences is in the proper order:




A: Define scope, estimate activity duration, estimate resources, determine budget

B: Collect requirements, develop human resource plan, estimate activity duration, sequence activities

C. Collect requirements, define scope, determine budget, sequence activities

D. Collect requirements, define scope, create WBS, define activities, sequence activities


Answer: D