The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project.


a. longest; longest
b. longest; shortest
c. shortest; longest
d. shortest; shortest

Answer: longest; shortest

____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.


a. Crushing
b. Crashing
c. Fast tracking
d. Expediting

Answer: Crashing

____ involves doing activities in parallel that you would normally do in sequence.


a. Crushing
b. Crashing
c. Fast tracking
d. Expediting

Answer: Fast tracking

____ states that work expands to fill the time allowed.


a. Murphy's Law
b. Newton's Law
c. Parkinson's Law
d. Moore's Law

Answer: Parkinson's Law

The goal of ____ is to know the status of the schedule, influence the factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur.


a. activity duration estimating
b. schedule development
c. schedule control
d. activity resource estimating

Answer: schedule control