The ____ is a network diagramming technique in which boxes represent activities.
a. PDM
b. AOA
c. ADM
d. POA
Answer: PDM
In a ____ relationship, one task cannot finish before another finishes.
a. start-to-start
b. finish-to-start
c. finish-to-finish
d. start-to-finish
Answer: finish-to-finish
A ____ is a hierarchical structure that identifies the project's resources by category and type.
a. work breakdown structure
b. resource breakdown structure
c. network diagram
d. critical path analysis
Answer: resource breakdown structure
The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.
a. defining activities
b. sequencing activities
c. developing the schedule
d. estimating activity duration
Answer: developing the schedule
____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
a. Gantt charts
b. Critical path analysis
c. Critical chain scheduling
d. PERT analysis
Answer: Gantt charts