___ involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule.
a. Estimating activity durations
b. Developing the schedule
c. Controlling the schedule
d. Estimating activity resources
Answer: Developing the schedule
____ results in supporting detail to document important product information as well as assumptions and constraints related to specific activities.
a. Defining activities
b. Sequencing activities
c. Estimating activity resources
d. Estimating activity duration
Answer: Defining activities
____ dependencies are inherent in the nature of the work being performed on a project.
a. Mandatory
b. Discretionary
c. External
d. Internal
Answer: Mandatory
____ dependencies involve relationships between project and non-project activities.
a. Mandatory
b. Discretionary
c. External
d. Internal
Answer: External
____ occur when two or more activities follow a single node.
a. Combinations
b. Conflicts
c. Merges
d. Bursts
Answer: Bursts