The final step in the creation of a Work Breakdown Structure is to
A. Code the WBS for tracking
B. Assign the cost account to a manager
C. Assign the work package to a manager
D. Develop the responsibility matrix
E. All of these are included in the final step
Answer: Code the WBS for tracking