The intersection of the WBS and the OBS is called the
A. Responsibility matrix
B. Priority matrix
C. Work package
D. Cost account
E. Project overlap
Answer: Cost account
A. Responsibility matrix
B. Priority matrix
C. Work package
D. Cost account
E. Project overlap
Answer: Cost account