You are managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of .94. How would you BEST describe this project?

You are managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of .94. How would you BEST describe this project?



A. The project is ahead of scheule and within its budget.

B. The project is behind schedule and within its budget.

C. The project is ahead of schedule and over its budget.

D. The project is behind schedule and over its budget.


Answer: SPI is greater than 1, you are ahead of schedule. CPI is less than 1, you are over budget. (C)