Which of the following is the BEST thing to do to try to complete a project two days earlier?

Which of the following is the BEST thing to do to try to complete a project two days earlier?


A. Tell senior management that the project's critical path does not allow the project to be finished earlier
B. Tell your boss
C. Meet with the team and look for options for crashing or fast tracking the critical path
D. Work hard and see what the project status is next month


Answer C