Which of the following is a benefit of an analogous project estimate?

Which of the following is a benefit of an analogous project estimate?




A. The estimate will be closer to what the work will actually require
B. It is based on a detailed understanding of what the work requires
C. It gives the project team an understanding of management's expectations
D. It helps the project manager determine if the project will meet the schedule


Answer C

Senior management is complaining that they are not able to easily determine the status of ongoing projects in the organization. Which of the following types of reports would help provide summary information to senior management?

Senior management is complaining that they are not able to easily determine the status of ongoing projects in the organization. Which of the following types of reports would help provide summary information to senior management?


A. Detailed cost estimates
B. Project management plans
C. Bar charts
D. Milestone reports



Answer D