During project executing, a large number of changes are made to the project. The project manager should:

During project executing, a large number of changes are made to the project. The project manager should:


A. Wait until all changes are known and print out a new schedule
B. Make approved changes as needed, but retain the schedule baseline
C. Make only the changes approved by management
D. Talk to management before any changes are made


Answer B


Learn More :