Project Management Questions and Answer

A(n) ____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.

a. project charter
b. business case
c. project scope statement
d. work breakdown structure

Answer: work breakdown structure

In the ____, you use a similar project's WBS as a starting point.

a. top-down approach
b. bottom-up approach
c. mind-mapping approach
d. analogy approach

Answer: analogy approach

The ____ approach is best suited to project managers who have vast technical insight and a big-picture perspective.


a. analogy
b. bottom-up
c. top-down
d. mind mapping

Answer: top-down

____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.


a. Prototyping
b. JAD
c. RAD
d. Use case modeling

Answer: Use case modeling

The main outputs of the ____ process are an activity list, activity attributes, and milestone list.


a. defining activities
b. sequencing activities
c. resource estimating activities
d. duration estimating activities

Answer: defining activities