Companies like Boeing, Kodak, and IBM are using which of the following for improving the estimating process?

Companies like Boeing, Kodak, and IBM are using which of the following for improving the estimating process? 


A. Adjusting estimates based on individual forecasting abilities

B. Benchmarking using the experience of other companies

C. Using time and motion studies

D. Creating historical databases of previous projects

E. All of these are correct


Answer: Creating historical databases of previous projects

Which of the following is not one of the recommended guidelines for developing useful work package estimates?

Which of the following is not one of the recommended guidelines for developing useful work package estimates? 


A. Estimates should be made by those responsible for the work

B. Use several people to estimate the same work

C. Estimates should be based on normal conditions

D. Estimates should include a normal level of contingency

E. Estimates should be independent of other projects


Answer: D. Estimates should include a normal level of contingency

Which of the following would be considered a direct project cost?

Which of the following would be considered a direct project cost? 


A. Labor

B. Materials

C. Equipment

D. Both A and B are direct costs

E. A, B, and C are all considered direct costs


Answer: A, B, and C are all considered direct costs

Typical kinds of costs found in a project include

Typical kinds of costs found in a project include 


A. Direct costs

B. Project overhead costs

C. General and administrative costs

D. Only A and B are included

E. A, B, and C are all included


Answer: A, B, and C are all included