Scott has just been given a project that has a specific target date. After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The target date is best classified as

Scott has just been given a project that has a specific target date. After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The target date is best classified as 


A. Constrain

B. Enhance

C. Accept

D. Limit

E. Optional


Answer: accept