If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?

If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice? 


A. Responsibility matrix

B. Organization breakdown structure

C. Work breakdown structure

D. Priority matrix

E. Process breakdown structure


Answer: Responsibility matrix