If a project is small or of narrow scope and does not require an elaborate system, which of the following is a good choice?
A. Responsibility matrix
B. Organization breakdown structure
C. Work breakdown structure
D. Priority matrix
E. Process breakdown structure
Answer: Responsibility matrix