A work breakdown structure numbering system allows the project staff to:

A work breakdown structure numbering system allows the project staff to: 


A. Systematically estimate costs of work breakdown structure elements
B. Provide project justification
C. Identify the level at which individual elements are found
D. Use it in project management software


Answer C