The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.

The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.



a. defining activities
b. sequencing activities
c. developing the schedule
d. estimating activity duration


Answer: developing the schedule