Project Management Questions and Answer

A(n) ____ is a document that describes the products or services to be created by the project team.

a. contract
b. statement of work
c. project charter
d. business case

Answer: statement of work

The ____ section of the project management plan describes how to monitor project progress and handle changes.

a. management objectives
b. project controls
c. risk management
d. technical processes

Answer: project controls

The ____ section of the project management plan describes specific methodologies a project might use and explains how to document information.

a. management objectives
b. project controls
c. risk management
d. technical processes

Answer: technical processes

The project schedule information section of the project management plan might include ____.

a. a detailed budget
b. key deliverables
c. a detailed schedule
d. project staffing

Answer: a detailed schedule

Most systems analysts begin their careers as ____.

a. database administrators
b. CEOs
c. project managers
d. programmers

Answer: programmers