A(n) ____ is a document that describes the products or services to be created by the project team.
a. contractb. statement of work
c. project charter
d. business case
Answer: statement of work
The ____ section of the project management plan describes how to monitor project progress and handle changes.
a. management objectivesb. project controls
c. risk management
d. technical processes
Answer: project controls
The ____ section of the project management plan describes specific methodologies a project might use and explains how to document information.
a. management objectivesb. project controls
c. risk management
d. technical processes
Answer: technical processes
The project schedule information section of the project management plan might include ____.
a. a detailed budgetb. key deliverables
c. a detailed schedule
d. project staffing
Answer: a detailed schedule