In reviewing the project plan, Susan sees that the first prototype is due by October 12. This would be best classified as a
A. Project target
B. Limit item
C. Milestone
D. Project objective
E. Critical goal
Answer: Milestone
A. Project target
B. Limit item
C. Milestone
D. Project objective
E. Critical goal
Answer: Milestone