The project is calculated to be completed four days after the desired completion date. You do not have access to additional resources. The project is low risk, the benefit cost ratio (BCR) is expected to be 1.6, and the dependencies are preferential. Under these circumstances, what would be the BEST thing to do?


A. Cut resources from an activity
B. Make more activities concurrent
C. Move resources from the preferential dependencies to the external dependencies
D. Remove an activity from the project


Answer B


Learn More :