One of the stakeholders on the project contacts the project manager to discuss some additional scope they would like to add to the project. The project manager asks for details in writing and then works through the Control Scope process. What should the project manager do NEXT when the evaluation of the requested scope is complete?

One of the stakeholders on the project contacts the project manager to discuss some additional scope they would like to add to the project. The project manager asks for details in writing and then works through the Control Scope process. What should the project manager do NEXT when the evaluation of the requested scope is complete? 


A. Ask the stakeholder if there are any more changes expected
B. Complete integrated change control
C. Make sure the impact of the change is understood by the stakeholder
D. Find out the root cause of why the scope was not discovered during project planning



Answer B