A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?

A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?


A. Critical path method
B. PERT
C. Monte Carlo
D. Resource leveling



Answer B