A project manager is in the middle of the executing process of a very large construction project when he discovers that the time needed to complete the project is longer than the time available. What is the BEST thing to do?

A project manager is in the middle of the executing process of a very large construction project when he discovers that the time needed to complete the project is longer than the time available. What is the BEST thing to do? 


A. Cut product scope
B. Meet with management and tell them that the required date cannot be met
C. Work overtime
D. Determine options for schedule compression and present management with his recommended option


Answer D