A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?

A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?


A. Change requests
B. Schedule change control system
C. Recommended corrective actions
D. Reserves


Answer D