A project has three critical paths. Which of the following BEST describes how this affects the project?
A. It makes it easier to manage
B. It increases the project risk
C. It requires more people
D. It makes it more expensive
Answer B
Learn More :
PMP Chapter 5
- During project executing, a large number of changes are made to the project. The project manager should:
- Which of the following is a benefit of an analogous project estimate?
- Rearranging resources so that a constant number of resources is used each month is called:
- Senior management is complaining that they are not able to easily determine the status of ongoing projects in the organization. Which of the following types of reports would help provide summary information to senior management?
- A project manager for a small construction company has a project that was budgeted for $130,000 over a six-week period. According to her schedule, the project should have cost $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the PRIMARY responsibility to solve this problem?
- An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. The activity:
- A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the labor hours per installation from past projects to predict the future. This is an example of which of the following?
- You are a project manager for a new product development project that has four levels in the work breakdown structure. A network diagram has been created, the duration estimates have been compressed, and a schedule has been developed. What time management activity should you do NEXT?
- A new product development project has four levels in the work breakdown structure and has been sequenced using the precedence diagramming method. The activity duration estimates have been received. What should be done NEXT?
- The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project manager to do?
- A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?
- A project manager is taking over a project from another project manager during the planning process group. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be BEST to look at the:
- A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?
- You have a project with the following activities: Activity A takes 40 hours and can start after the project starts. Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities Band C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is TRUE if activity B actually takes 37 hours?
- You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following BEST describes what this type of input is called?
- You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
- During project planning, you estimate the time needed for each activity and then add the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?
- A project manager is in the middle of the executing process of a very large construction project when he discovers that the time needed to complete the project is longer than the time available. What is the BEST thing to do?
- Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity?
- In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:
- Which of the following is the BEST thing to do to try to complete a project two days earlier?
- Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?
- When would a milestone chart be used instead of a bar chart?
- If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?