Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion.
When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs associated with transferring the workers are an example of project indirect costs.
Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project. (T/F)