Which of the following represents the estimated value of the work actually accomplished? PMP Chapter 6 Which of the following represents the estimated value of the work actually accomplished? A. Earned value (EV) B. Planned value (PV) C. Actual cost (AC) D. Cost variance (CV) Answer A Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+