Analogous estimating: PMP Chapter 6 Analogous estimating: A. Uses bottom-up estimating techniques B. Is used most frequently during the executing processes of the project C. Uses top-down estimating techniques D. Uses actual detailed historical costs Answer C Learn More : Share this Share on FacebookTweet on TwitterPlus on Google+