A project manager has just taken over the project from another project manager during the execution of the project. The previous project manager created a project budget, determined communications requirements, and went on to complete work packages. What should the new project manager do NEXT?

A project manager has just taken over the project from another project manager during the execution of the project. The previous project manager created a project budget, determined communications requirements, and went on to complete work packages. What should the new project manager do NEXT?


A. Coordinate completion of work packages
B. Identify quality standards
C. Begin the Identify Risk process
D. Execute the project management plan


Answer B