A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do?

A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do?




A. Fix the problem as soon as possible
B. Allow the schedule to slip by cutting cost
C. Allow cost to increase by fixing the root cause of the problem
D. Allow risk to increase by cutting cost


Answer C