A project manager has just been assigned to a new project and has been given the project charter. The FIRST thing the project manager must do is:
A. Create a project scope statement
B. Confirm that all the stakeholders have had input into the scope
C. Analyze project risk
D. Begin work on a project management plan
Answer B