A defect in the product was brought to the project manager's attention and now the project team is engaged in repairing it. Which project management process would be the most applicable to this?

A defect in the product was brought to the project manager's attention and now the project team is engaged in repairing it. Which project management process would be the most applicable to this?


A. Perform Integrated Change Control
B. Monitor and Control Project Work
C. Direct and Manage Project Execution
D. Close Project or Phase


Answer - C - as it is also including fixing it / doing work