You are taking over a project and determine the following: Activity B has an early finish (EF) of day 3, a late finish (LF) of day 6 and an early start of day 2. Activity L is being done by a hard-to-get resource. The cost performance index (CPI) is 1.1, and the schedule performance index (SPI) is 0.8. Based on this information, what would you be more concerned about?

You are taking over a project and determine the following:
Activity B has an early finish (EF) of day 3, a late finish (LF) of day 6 and an early start of day 2.
Activity L is being done by a hard-to-get resource.
The cost performance index (CPI) is 1.1, and the schedule performance index (SPI) is 0.8.
Based on this information, what would you be more concerned about?




A. Float
B. Resources
C. Cost
D. Schedule



Answer D