If the project manager then evaluates whether the variance warrants a response, he is in what project management process?

A project manager gets a call from a team member notifying him that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning.

If the project manager then evaluates whether the variance warrants a response, he is in what project management process?




A. Initiating
B. Executing
C. Monitoring and controlling
D. Closing



Answer C