For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Which of the following statements is true?

For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Which of the following statements is true?



A. The Late Finish is 12
B. The Early Finish is 10
C. The slack for this activity is 2
D. The duration of this activity is 2
E. The activity is on the critical path






Answer: C


Learn More :